Karak Highway, Kuala Lumpur, Malaysia
WCT Berhad was involved in the upgrading works of the Kuala Lumpur-Karak Highway. The scope of work includes preliminaries and general items; site clearance and earthworks; drainage, culverts and miscellaneous works; box culverts; erection of reinforced earth retaining walls and subbase works.

The Upgrading of Kuala Lumpur – Karak Highway
Contract Sum : RM 32.5 million
Construction Period : 15 October 1994 to 14 April 1996 (Extended Contract)
Scope of Works : Earthworks and Ancillary Works for Section 1A (CH 0+6200), Section 2B - Partial (CH 34+100 to CH 43+000) and Section 2C (CH 43+000 to CH 60+000)